What Is the TOKYO CROSS PARK Vision? Master Plan and Latest Developments for the Uchisaiwaicho 1-Chome District

Discover the TOKYO CROSS PARK vision — Tokyo's largest urban redevelopment at approximately 1.1 million m². Get the latest on the South District South Tower (broke ground April 2025), NTT Hibiya Tower (broke ground December 2025), and progress across all three districts.

Last updated: About 5 min read

The "TOKYO CROSS PARK" vision, underway in Uchisaiwaicho 1-chome, Chiyoda City, Tokyo, is Japan's largest urban redevelopment project, with a total gross floor area of approximately 1.1 million m². In 2025 alone, construction began on two supertall towers — the South District South Tower in April and the Central District NTT Hibiya Tower in December. This article provides a comprehensive overview of the master plan across all three districts, the latest construction schedule, and the project's implications for the real estate market.

Overview of the TOKYO CROSS PARK Vision — A 1.1 Million m² District Transformation in Central Tokyo

The Uchisaiwaicho 1-chome district covers approximately 6.5 hectares in Uchisaiwaicho 1-chome, Chiyoda City, Tokyo. Situated at a rare crossroads where the major districts of Otemachi, Marunouchi, Yurakucho, Ginza, Kasumigaseki, and Shimbashi converge, the plan calls for a mixed-use district with a total gross floor area of approximately 1.1 million m². As the largest single project of its kind in Japan, it will significantly shape the future of urban development in central Tokyo.

The project consortium comprises ten companies: NTT Urban Solutions, Inc., Public Buildings Co., Ltd., Dai-ichi Life Insurance Company, Chuo-Nittochi Co., Ltd., Imperial Hotel, Ltd., Tokyo Century Corporation, Tokyo Electric Power Company Holdings, Inc., Nippon Telegraph and Telephone Corporation, Nippon Telegraph and Telephone East Corporation, and Mitsui Fudosan Co., Ltd. A coalition of ten private-sector companies collaborating on urban regeneration at this scale is unprecedented — not only in terms of sheer size, but also as a model for managing complexity and distributing risk.

The master design for the entire district was entrusted to PLP Architecture, a UK-based firm, and the name "TOKYO CROSS PARK" embodies three meanings of "CROSS." The plan envisions four supertall towers built in phases across three districts — North, Central, and South — with full completion projected for fiscal year 2037 or later.

TOKYO CROSS PARK vision for Uchisaiwaicho 1-chome district — aerial rendering of completed development
Uchisaiwaicho 1-chome district — completed development rendering (Source: NTT Urban Development press release, December 2025)

South District South Tower — Large-Scale Mixed-Use Tower Scheduled for Completion in March 2029

The first of the three districts to break ground was the South District "South Tower." Designated under urban planning as the Uchisaiwaicho 1-Chome South District Category I Urban Redevelopment Project, construction by Shimizu Corporation commenced on April 1, 2025, with completion scheduled for the end of March 2029.

The building rises 46 stories above ground with one penthouse level and three basement levels, reaching approximately 227 meters in height (232 meters at its highest point), with a total gross floor area of approximately 290,000 m². The mixed-use composition centers on office space (floors 11–44, with approximately 150,000 m² of leasable area), complemented by a hotel (floors 4–6), retail facilities (floors 1–3), and wellness amenities (floors 7–8). Direct connection to Uchisaiwaicho Station will serve as a key differentiator in attracting tenants.

Particularly noteworthy is the planned world-first practical deployment of perovskite solar cells. By integrating this next-generation solar technology into the exterior walls of a supertall building, the project aims to advance both energy self-sufficiency and decarbonization — a flagship initiative that embodies the "CROSS innovation" concept.

Central District NTT Hibiya Tower — Broke Ground December 2025, a New 360,000 m² Landmark

On December 1, 2025, construction began on the NTT Hibiya Tower. Developed jointly by NTT Urban Development and Tokyo Electric Power Grid, this building will be the largest of the three districts at 48 stories, approximately 229 meters tall (233 meters at its highest point), with a total gross floor area of approximately 360,000 m². Completion is scheduled for the end of October 2031.

The building combines offices with industrial support facilities, a hall, banquet venues, a hotel, and retail space. Beyond serving as a business hub, it is designed to function as a center for culture and exchange. The project carries significant strategic importance for the NTT Group, transforming long-held land assets in the Kasumigaseki area into a vehicle for urban regeneration.

What makes this tower especially compelling is the planned connection to Hibiya Park via an elevated park over the roadway, tentatively called "Cross Gate." This physical link between the district and the park will create walkable circulation routes throughout the area. Rather than simply constructing buildings, this approach — integrating surrounding public spaces to reshape an entire neighborhood — represents a model for large-scale redevelopment today.

NTT Hibiya Tower — view from upper office floors overlooking Hibiya Park and the Imperial Palace outer gardens
NTT Hibiya Tower — rendering of the view from upper office floors (Source: NTT Urban Development press release, December 2025)

North District and the New Imperial Hotel Main Building — A "New State Guest House" Slated for Completion in Fiscal 2036

Two buildings are planned for the North District. The North Tower (46 stories, approximately 230 meters tall) is expected to break ground around 2026, with completion in fiscal 2030. The new Imperial Hotel Main Building (29 stories, approximately 145 meters tall) is projected to begin construction in fiscal 2031 and be completed in fiscal 2036.

The design architect for the new Imperial Hotel Main Building is Tsuyoshi Tane (ATTA – Atelier Tsuyoshi Tane Architects). Under the concept of "a new grand hotel and state guest house," the design aims to honor the legacy of the Imperial Hotel — with over 134 years of history — while reimagining it for the urban landscape of the 21st century. The reconstruction cost for the Imperial Hotel portion alone has been announced at approximately ¥200–250 billion, a figure that speaks to the project's extraordinary scale.

The Imperial Hotel plans to continue operations throughout the reconstruction period. For one of Japan's most iconic hotel brands to maintain service during construction is a critical decision for preserving the prestige and drawing power of the area.

Integrated Urban Development with Hibiya Park

What sets the TOKYO CROSS PARK vision apart is its integrated development approach with Hibiya Park, which spans approximately 16 hectares. Centered on the Central District, an elevated park built above the roadway will physically connect the district to the park. Additionally, a large-scale plaza of approximately 2 hectares is planned atop the podium structures, creating gathering spaces not only for office workers but also for local residents and visitors.

This initiative is coordinated with the Tokyo Metropolitan Government Bureau of Construction's "Hibiya Park Revitalization and Improvement Plan." In other words, public and private sectors are working together to transform the broad area from Kasumigaseki to Ginza into a green, walkable city. However, whether this vision truly succeeds will depend on post-completion operations management and how well the public spaces are actually used. The real test will come in the years ahead, when sustained investment in programming and placemaking — not just physical infrastructure — will be essential.

Rendering of the elevated park over the roadway connecting the district and Hibiya Park
Rendering of the elevated park connecting the district and Hibiya Park (Source: NTT Urban Solutions "TOKYO CROSS PARK Vision — Plan Overview", March 2022)

Development Schedule Summary

District Building Construction Start Estimated Completion
South District South Tower (46 stories, approx. 230 m tall) April 2025 March 2029
Central District NTT Hibiya Tower (48 stories, approx. 233 m tall) December 2025 October 2031
North District North Tower (46 stories, approx. 230 m tall) Around 2026 Fiscal 2030
North District Imperial Hotel New Main Building (29 stories, approx. 145 m tall) Fiscal 2031 Fiscal 2036

From 2025 through 2031, the Uchisaiwaicho 1-chome district will see a continuous cycle of construction vehicles and scaffolding. Businesses, investors, and residents operating in the area should be prepared for long-term impacts on traffic flow and the local environment.

Impact on Surrounding Areas and Implications for the Real Estate Market

The Uchisaiwaicho 1-chome district sits near the intersection of Chiyoda, Minato, and Chuo wards — Tokyo's three core central wards — giving it the potential to influence real estate markets across multiple major districts. On the office front, the South District alone will bring approximately 150,000 m² of leasable space to market, and when combined with NTT Hibiya Tower, a substantial volume of new supply will hit the market between 2029 and 2031.

Large-scale new supply generally drives vacancy rates up and puts downward pressure on rents. However, this district's high-spec buildings, direct station access, and park-integrated location may attract Grade A tenants. In fact, the opposite effect could occur: existing buildings in the Marunouchi and Otemachi areas may face relative obsolescence, accelerating renovation and repurposing initiatives — a chain reaction across the market. For a deeper analysis of how urban redevelopment in central Tokyo affects property values, see this article.

The concentration of retail and hotel uses also warrants attention. The temporary reduction in capacity during the Imperial Hotel reconstruction, the impact on the luxury hotel market once the new main building opens, and the boost to foot traffic in the Hibiya and Yurakucho areas from the retail zones will all exert complex influences on medium- to long-term rent formation — including potential synergies with the Yurakucho Station area redevelopment.

The course of action for property owners is clear. Those with holdings in the Uchisaiwaicho, Hibiya, Kasumigaseki, or Shimbashi areas should start by mapping the completion milestones (2029, 2031, 2036) against their own asset plans. To maintain competitiveness during a period of expanding supply, it is important to begin evaluating the timing of spec upgrades, adjustments to tenant lease renewal cycles, or potential dispositions and portfolio rebalancing sooner rather than later.

Frequently Asked Questions (FAQ)

Q1. When will the entire TOKYO CROSS PARK project be completed?

A. Full completion of the district is scheduled for fiscal 2037 or later. The South District South Tower will be the first to finish in March 2029, followed by the Central District NTT Hibiya Tower in October 2031, the North District North Tower in fiscal 2030, and the Imperial Hotel New Main Building in fiscal 2036. Because the project is completed in phases, the area's transformation will unfold over an extended period from the late 2020s through the 2030s.

Q2. What is the total gross floor area of the TOKYO CROSS PARK project?

A. The total gross floor area is approximately 1.1 million m², making it Japan's largest urban development as a single project. Four supertall towers will be built across three districts — North, Central, and South — housing a mixed-use complex of offices, hotels, retail, wellness facilities, and industrial support spaces. For comparison, Tokyo Midtown has a gross floor area of approximately 560,000 m², meaning this project is nearly twice that scale.

Q3. How will the district connect to Hibiya Park?

A. The district will be physically connected to Hibiya Park via an elevated park built above the roadway, centered on the Central District. A large-scale plaza of approximately 2 hectares will also be developed atop the podium structures, creating walkable routes where the district's greenery flows seamlessly into the park. This is being carried out in coordination with the Tokyo Metropolitan Government Bureau of Construction's "Hibiya Park Revitalization and Improvement Plan" as a joint public-private initiative.

Q4. Will the Imperial Hotel remain open during reconstruction?

A. The Imperial Hotel plans to continue operations throughout the reconstruction period. The rebuild will proceed in phases, utilizing temporary facilities within the North District North Tower. However, some reduction in scale and relocation of certain services will occur, so guests are advised to check the Imperial Hotel's official announcements for the latest information. The new main building is scheduled for completion in fiscal 2036.

References

1. Tokyo Metropolitan Government Bureau of Urban Development, "Uchisaiwaicho 1-Chome South District Category I Urban Redevelopment Project"

2. Tokyo Metropolitan Government Bureau of Environment, "(Tentative Name) Uchisaiwaicho 1-Chome District Development Plan (South District)"

3. Chiyoda City, "Uchisaiwaicho 1-Chome District Urban Development Guidelines (Draft)" (PDF)

4. Tokyo Metropolitan Government Bureau of Construction, "Hibiya Park Revitalization and Improvement"

5. NTT Urban Solutions, "TOKYO CROSS PARK Vision" Official Website

6. NTT Urban Solutions, "TOKYO CROSS PARK Vision — Plan Overview"

7. NTT Urban Development, "Uchisaiwaicho 1-Chome Central District NTT Hibiya Tower Construction Commencement" (December 8, 2025)

8. NTT Urban Solutions, "NTT Hibiya Tower Construction Commencement" News Release (December 2025)

9. Chuo-Nittochi Co., Ltd., "Uchisaiwaicho 1-Chome South District Category I Urban Redevelopment Project Groundbreaking" (April 3, 2025)

10. Dai-ichi Life Insurance, "Uchisaiwaicho 1-Chome South District Category I Urban Redevelopment Project Groundbreaking" (April 3, 2025, PDF)

11. Imperial Hotel, "Plan for Continued Operations During Reconstruction of Tokyo Properties" (PDF)

12. NTT East, "Announcement of TOKYO CROSS PARK Vision" (March 24, 2022)

Daisuke Inazawa, President & CEO of INA&Associates Inc.

Author

President & CEOINA&Associates Inc.

President & CEO of INA&Associates Inc. Leads real estate brokerage, rental leasing, and property management across Greater Tokyo and the Kansai region. Specialises in income-property investment strategy and advisory for ultra-high-net-worth individuals.

Daisuke Inazawa is the President and CEO of INA&Associates Inc., a Japanese real estate firm headquartered in Osaka with a Tokyo branch. He leads the company's three core businesses — real estate sales brokerage, rental leasing, and property management — across the Greater Tokyo Area and the Kansai region.

His areas of expertise include investment strategy for income-generating real estate, profitability optimisation of rental operations, real estate advisory for ultra-high-net-worth individuals (UHNWIs) and institutional investors, and cross-border real estate investment. He provides data-driven, long-horizon advisory to investors in Japan and overseas.

Under the management philosophy "a company's most important asset is its people," he positions INA&Associates as a "people-investment company" and is committed to sustainable corporate-value creation through talent development. He also writes and speaks publicly on leadership and organisational culture in times of change.

He has passed eleven Japanese professional qualification examinations: Licensed Real Estate Broker (Takken), Certified Real Estate Consulting Master, Licensed Condominium Manager, Licensed Building Management Supervisor, Certified Rental Housing Management Professional, Gyōseishoshi Lawyer (administrative scrivener), Certified Personal Information Protection Officer, Class-A Fire Prevention Manager, Certified Auctioned Real Estate Specialist, Certified Condominium Maintenance Engineer, and Licensed Moneylending Operations Supervisor.

  • Licensed Real Estate Broker (Takken)
  • Certified Real Estate Consulting Master
  • Licensed Condominium Manager
  • Licensed Building Management Supervisor
  • Certified Rental Housing Management Professional
  • Gyōseishoshi Lawyer (Administrative Scrivener)
  • Certified Personal Information Protection Officer
  • Class-A Fire Prevention Manager
  • Certified Auctioned Real Estate Specialist
  • Certified Condominium Maintenance Engineer
  • Licensed Moneylending Operations Supervisor