Keikyu Kamata West Exit Redevelopment | Urban Plan Approved 2025, Completion by 2032

A comprehensive guide to the Keikyu Kamata Center Area North District Type 1 Urban Redevelopment Project. Urban planning approved in December 2025 with completion targeted for 2032. Learn about Mitsui Fudosan Residential's involvement, the KAMATA UP TERRACE concept, and synergies with the Kamakama Line.

Last updated: About 6 min read

A new urban redevelopment project is entering its full launch phase in the west exit area of Keikyu Kamata Station, designated as a "central hub" of Ota City, Tokyo. The "Keikyu Kamata Center Area North District Type 1 Urban Redevelopment Project," for which the urban planning decision was officially announced on December 12, 2025, is a large-scale initiative aiming to build a mixed-use complex with approximately 46,000 square meters of total floor area, 21 stories above ground, and 480 residential units. Adding further momentum, in October 2025 the Ministry of Land, Infrastructure, Transport and Tourism approved the project plan for the "Shin-Airport Line (Kamakama Line)" connecting JR Kamata and Keikyu Kamata, elevating both the profile and real estate value of the entire area.

How Has the Keikyu Kamata West Exit Redevelopment Progressed in Two Phases?

To understand the transformation of Keikyu Kamata Station's west exit, it is essential to look back at Phase 1, which was completed in 2015. The redevelopment of this area was not a single undertaking but rather a phased effort spanning approximately 20 years.

Phase 1: West Exit Station Front Redevelopment Completed in 2015 (Proud City Kamata)

Following the establishment of the "Keikyu Kamata West Exit District Community Development Study Group" in 1999, years of collaboration among local residents, the municipal government, and developers culminated in the completion of the "Keikyu Kamata West Exit Station Front District Type 1 Urban Redevelopment Project" in December 2015. With Nomura Real Estate and Sumitomo Corporation participating as member partners, "Proud City Kamata" was born — a 20-story building with one basement level, standing 73.50 meters tall and containing 320 residential units. Floors 1 through 3 house commercial facilities while floor 4 and above are residential, creating a highly convenient mixed-use complex directly connected to Keikyu Kamata Station via a pedestrian deck and serving as the face of the west exit. This project was made possible by the completion of the full grade separation of the Keikyu Line near Kamata Station in 2012, representing the cumulative results of steady urban infrastructure development around the station.

Phase 2: The Center Area North District Redevelopment Currently Underway

Approximately 10 years after the completion of Phase 1, a new redevelopment project has been launched in the adjacent area to the north. The "Keikyu Kamata Center Area North District Redevelopment Preparatory Association" was established in 2020, and preparations began in earnest. On December 12, 2025, the urban planning decision was officially announced as a Ota City designation. This urban planning decision encompassed three announcements: the Type 1 urban redevelopment project designation, modifications to the high-utilization district, and amendments to the district plan — establishing the legal foundation for the project.

Project Overview — What Are the Site, Scale, and Facility Plans?

Project Area and Size

The project area covers blocks 3 through 9 of Kamata 4-chome, Ota City, Tokyo (around Kamata 4-5-9), with a total project area of approximately 0.6 hectares (6,000 m²). The site area is approximately 5,130 m² with a building footprint of about 3,570 m². While somewhat smaller than the Phase 1 west exit station front district (approximately 1.0 hectares), this project is notably challenging as it is being carried out in close proximity to the existing urban fabric.

Building Scale and Uses

Keikyu Kamata Center Area North District facility plan overview
Facility plan overview (Source: Keikyu Kamata Center Area North District Redevelopment Preparatory Association Official Website)

The planned building will have one basement level and 21 above-ground floors, standing approximately 75 meters tall with a total floor area of approximately 46,180 m² (about 46,000 m²). The uses are as follows. Basement level 1 will contain bicycle parking, a meeting hall, and vehicle parking. Floors 1 and 2 above ground are planned as commercial facilities expected to serve the daily shopping needs of local residents. Floors 4 through 21 will comprise 480 residential units, exceeding the supply scale of Phase 1's Proud City Kamata (320 units).

The Three Pillars of the "KAMATA UP TERRACE" Concept

The project's concept name is "KAMATA UP TERRACE," expressing the ambition to "update" the Kamata area and create open, terrace-like spaces. The three pillars supporting this concept are: (1) creating a walkable city with vibrant activity and relaxation spaces, (2) rebranding Kamata to enhance its community strength, and (3) pursuing sustainable urban development aligned with the SDGs. The vision extends beyond simply replacing buildings to reconstructing the "Kamata" brand itself — an approach worth noting from the perspective of long-term area value enhancement.

Project Timeline and Current Status — When Will Construction Start and Finish?

Urban redevelopment project flow (Ota City)
Project flow (Source: Ota City "Keikyu Kamata Center Area North District Urban Development")

From the 2020 Preparatory Association Establishment to the December 2025 Urban Planning Decision

This project began taking shape in 2018 with the establishment of the "Keikyu Kamata Center Area North District Joint Development Study Council." The preparatory association was then established in 2020, and community briefing sessions were held in 2023. In January and February 2025, urban planning draft briefing sessions were conducted over two days with a total of 155 participants, followed by the official urban planning decision announcement on December 12 of the same year. From initial concept to urban planning approval took approximately seven years — the result of persistent, ground-up consensus building.

What Comes Next — Association Establishment, Rights Conversion, 2028 Construction Start, 2032 Completion

As of the current stage (March 2026), activities are underway to establish the urban redevelopment association. Going forward, the process will involve association establishment approval, formulation and approval of rights conversion plans, and compensation and relocation negotiations, with construction targeted to begin in fiscal year 2028 (Reiwa 10). The completion target is 2032. Considering that urban redevelopment projects typically take three to five years from urban planning decision to construction start, this schedule can be considered pragmatic and well-grounded.

How Is the Project's Organizational Structure Configured?

The entity driving this project is the "Keikyu Kamata Center Area North District Redevelopment Preparatory Association." Two organizations are participating as project collaborators: the Metropolitan Area Fireproof Building Corporation (a general incorporated foundation) and Mitsui Fudosan Residential. The Metropolitan Area Fireproof Building Corporation is a public-sector entity with extensive experience in redevelopment projects within Tokyo, contributing to ensuring the project's public interest. Mitsui Fudosan Residential is a leading company in large-scale condominium development, expected to ensure the quality and marketability of the 480-unit residential component, whether for sale or lease. Notably, Nomura Real Estate participated as a member partner in Phase 1's west exit station front district, indicating sustained interest from major developers in this area.

Compared to similar projects underway in nearby areas of Tokyo, this project, while not the largest in scale, has demonstrated steady momentum from preparatory association establishment through to urban planning approval. Like the Tateishi Station North Exit Redevelopment | ¥128 Billion, 36-Story Tower and New Government Building and the Musashi-Koyama / Koyama 3-Chome Redevelopment | 39-Story Tower ¥96.3 Billion Plan, it represents one link in the chain of redevelopment spreading across southern Tokyo and the Jonan area.

How Significant Is the Synergy with the Kamakama Line (Shin-Airport Line)?

An external factor that cannot be overlooked when discussing this project is the advancement of the Shin-Airport Line (commonly known as the Kamakama Line). I believe this development will significantly influence the long-term value of the Center Area North District redevelopment.

Ministry of Land, Infrastructure, Transport and Tourism Approves Project Plan in October 2025 — Opening Target 2038–2042

On October 3, 2025, the Ministry of Land, Infrastructure, Transport and Tourism approved the "Speed Enhancement Plan" for the Shin-Airport Line. This officially launched the construction of the Kamakama Line, a new underground rail line of approximately 1.7 km connecting JR/Tokyu Kamata Station to Keikyu Kamata Station. The total project cost is approximately ¥124.8 billion, with a construction period from October 2025 to March 2042. The plan calls for phased construction, with Phase 1 running from Yaguchinowatashi to Keikyu Kamata and Phase 2 from Keikyu Kamata to Otorii, targeting an opening between 2038 and 2042. According to Ota City's estimates, the economic ripple effect in the first year of operation will be approximately ¥290 billion, with a cumulative total of approximately ¥570 billion over 10 years (per Ota City's "Shin-Airport Line (Kamakama Line)" main page).

Keikyu Kamata's Function as a Transportation Hub Will See a Dramatic Upgrade

Currently, JR Kamata (Tokyu Kamata) and Keikyu Kamata are approximately a 10-minute walk apart, requiring passengers to exit the stations to transfer. Once the Kamakama Line is realized, JR Kamata — where the Tokyu Tamagawa and Ikegami Lines converge — and Keikyu Kamata — served by the Keihin Express Main Line and Airport Line — will be directly connected via underground rail. This means access to Haneda Airport will improve dramatically from areas along the Tokyu Lines, leading to increased ridership at Keikyu Kamata Station itself and expanded commercial and residential demand. While the Center Area North District redevelopment targets completion in 2032, the Kamakama Line targets opening between 2038 and 2042. In other words, within just a few years of completion, the surrounding infrastructure will undergo major upgrades. This is precisely why I believe the long-term value of this area may be higher than current assessments suggest.

How Does This Fit Within Ota City's Master Plans?

Designated as a "Central Hub" and "Keikyu Kamata Station Front Hub"

The Ota City Urban Planning Master Plan designates the area around Keikyu Kamata Station as the city's "central hub." Additionally, the "Kamata Station Area Grand Design" positions the JR Kamata station front as the "Kamata Station Front Hub" and the Keikyu Kamata station front as the "Keikyu Kamata Station Front Hub," adopting an urban development policy that links these two cores. The Center Area North District redevelopment aligns with this policy, placing it in a favorable position to receive municipal support and coordination.

Streetscape-Guided District Plan Enables Autonomous Renewal in Surrounding Areas

In the areas surrounding the redevelopment project, a "streetscape-guided district plan" covering approximately 2.5 hectares has been applied, promoting individual building reconstruction through relaxed setback requirements and floor area ratios. Because mechanisms are in place for area-wide urban renewal to progress autonomously — not just through the large-scale redevelopment project — there is potential for continued improvement across the entire area even after the Center Area North District is completed.

Impact on Land Prices and the Real Estate Market — How Will Kamata's Value Change?

According to land price data, the 2025 officially assessed land price around Kamata Station has reached an average of approximately ¥1.6 million/m² (approximately ¥5.3 million per tsubo), recording a year-on-year increase of +8.14%. This outpaces the overall Ota City land price growth rate (+7.5%), positioning Kamata in the highest price bracket within the ward. The progress of redevelopment and expectations surrounding the Kamakama Line have been cited as primary drivers of the land price increase, with the year-on-year change in land transaction prices accelerating to +10.13% (figures based on official land price data).

Projected Housing and Commercial Demand After Redevelopment Completion

While 480 residential units will be supplied upon completion in 2032, new residential and commercial demand is expected to flow into the area between 2038 and 2042, coinciding with the Kamakama Line's opening. As competition intensifies among redevelopment projects in southern Tokyo and the Jonan area, Keikyu Kamata holds a rare locational advantage with its direct connection to Haneda Airport. Attention to this area will only continue to grow. As highlighted in Major Redevelopment Projects Transforming Tokyo in 2025, even amid Tokyo's broader redevelopment boom, the Haneda area is charting its own unique growth trajectory.

Frequently Asked Questions (FAQ)

Q1. When will the Keikyu Kamata Center Area North District redevelopment be completed?

Construction is targeted to begin in fiscal year 2028 (Reiwa 10), with completion aimed for 2032. Following the urban planning decision in December 2025, efforts are currently underway to establish the urban redevelopment association.

Q2. What kind of facilities will this redevelopment create?

A mixed-use complex with one basement level and 21 above-ground floors totaling approximately 46,000 m² is planned. Basement level 1 will house bicycle parking and a meeting hall, floors 1 and 2 will contain commercial facilities, and floors 4 through 21 will accommodate a total of 480 residential units. The building will stand approximately 75 meters tall.

Q3. Who is leading this redevelopment?

The Keikyu Kamata Center Area North District Redevelopment Preparatory Association serves as the project executor, with the Metropolitan Area Fireproof Building Corporation and Mitsui Fudosan Residential participating as project collaborators.

While there is no direct project partnership, the realization of the Kamakama Line would directly connect JR Kamata (Tokyu) and Keikyu Kamata via underground rail, significantly enhancing transportation convenience for the redeveloped facilities. The Ministry of Land, Infrastructure, Transport and Tourism approved the project plan in October 2025, targeting an opening between 2038 and 2042. This transportation infrastructure development is expected to further boost real estate values in the area.

Citations and References

Daisuke Inazawa, President & CEO of INA&Associates Inc.

Author

President & CEOINA&Associates Inc.

President & CEO of INA&Associates Inc. Leads real estate brokerage, rental leasing, and property management across Greater Tokyo and the Kansai region. Specialises in income-property investment strategy and advisory for ultra-high-net-worth individuals.

Daisuke Inazawa is the President and CEO of INA&Associates Inc., a Japanese real estate firm headquartered in Osaka with a Tokyo branch. He leads the company's three core businesses — real estate sales brokerage, rental leasing, and property management — across the Greater Tokyo Area and the Kansai region.

His areas of expertise include investment strategy for income-generating real estate, profitability optimisation of rental operations, real estate advisory for ultra-high-net-worth individuals (UHNWIs) and institutional investors, and cross-border real estate investment. He provides data-driven, long-horizon advisory to investors in Japan and overseas.

Under the management philosophy "a company's most important asset is its people," he positions INA&Associates as a "people-investment company" and is committed to sustainable corporate-value creation through talent development. He also writes and speaks publicly on leadership and organisational culture in times of change.

He has passed eleven Japanese professional qualification examinations: Licensed Real Estate Broker (Takken), Certified Real Estate Consulting Master, Licensed Condominium Manager, Licensed Building Management Supervisor, Certified Rental Housing Management Professional, Gyōseishoshi Lawyer (administrative scrivener), Certified Personal Information Protection Officer, Class-A Fire Prevention Manager, Certified Auctioned Real Estate Specialist, Certified Condominium Maintenance Engineer, and Licensed Moneylending Operations Supervisor.

  • Licensed Real Estate Broker (Takken)
  • Certified Real Estate Consulting Master
  • Licensed Condominium Manager
  • Licensed Building Management Supervisor
  • Certified Rental Housing Management Professional
  • Gyōseishoshi Lawyer (Administrative Scrivener)
  • Certified Personal Information Protection Officer
  • Class-A Fire Prevention Manager
  • Certified Auctioned Real Estate Specialist
  • Certified Condominium Maintenance Engineer
  • Licensed Moneylending Operations Supervisor